
Summer
2001
Settling
basins for open feedlots
by
Jeff Lorimor, Department of Ag and Biosystems Engineering
Current Iowa Department
of Natural Resources rules require all open feedlots to have settling
basins below them to settle out the settleable solids before any liquid
is allowed to leave. Proper settling basin design ensures good performance
and optimum operator convenience. Good design can help achieve both these
requirements.
Settling can occur
in basins, terraces, diversions, or other natural areas. The law specifies
the following minimum requirements:
- Basins must be
designed to settle solids from runoff from a 1-hour, 10-year storm (approximately
2.5 inches per hour).
- Liquid velocity
in the basin must be reduced to 0.5 foot per second or less for at least
5 minutes.
- Settling basins
must have 1 square foot of surface area for every 8 cubic feet of runoff
per hour from the feedlot.
- Basins must include
adequate capacity to store the settled solids between cleanouts.
Although these requirements
sound confusing, we can use some approximations to make settling basin
design relatively easy and still be sure to meet the requirements and
be effective. The two most important criteria are the storm size and the
basin surface area requirement.
Storm
size. The
1-hour, 10-year storm varies from 2.1 inches in the northeastern corner
of Iowa to 2.5 inches in
the southwestern corner. The storm size, lot slope, lot surface (earth
or concrete), and lot area determine the amount of runoff that occurs.
For such a large, intense storm, assume that 100 percent of the rainfall
runs off the lot. Using the conservative assumptions of 2.5 inches per
hour and 100 percent runoff ensures that the settling area will be large
enough.
Basin
surface area. The
second requirement, 8 square feet per cubic feet per hour runoff, coupled
with the storm size, determines the minimum basin size. The following
example shows a minimum settling basin design for a 1-acre lot using 100
percent runoff and 2.5 inches per hour:
(2.5 inches/hour)
x (1 acre) x (3,600 conversion factor*) = 9,000 cubic feet/hour
*1 acre-inch/hour = 1 cubic foot/second, and 3,600 seconds = 1 hour
By using the Department
of Natural Resoruces requirement of 8 square feet of surface area
for each cubic foot/hour, the minimum basin size = (9,000 cubic feet/hour)/8
= 1,125 square foot surface area.
We must add solids
storage to this area. (Notice that the ratio of the lot surface area to
the settling basin surface area is 43,560/1,125 = 39). The rule of thumb
for settling basins in Iowa
is as follows: the settling basin must be at least 1/40th of the lot drainage
area. This size is the absolute minimum size without any solids storage
added.
Now that we have determined
the size of the basin, we need to design it to maximize its effectiveness
and to be convenient to manage. To do so consider the following four criteria.
Slope.
Use a very flat slope so the flow slows immediately when it hits the
basin. Generally use from 0.5 percent (1/2 of 1 percent) or less slope.
Depth.
Settling basins typically should be fairly shallow to allow easy access
for cleanout. One to 2 feet is often used, but if the situation warrants,
deeper is fine. The shallower it is the more rapidly the solids will dry
down. Some situations require settling ponds or tanks rather than flat
basins. If you go deeper to more of a settling tank or pond, you must
have appropriate cleanout methods available such as a back hoe, dragline,
or track-type tractor.
Geometry.
Settling basins below small concrete lots may only be 8 to 10 feet in
width. Minimum width is the width of your loader bucket. Basins below
larger lots comprising several acres will more likely be 20 feet or more
in width. The length is determined by the length necessary to intercept
all the runoff across the bottom of the lot, or by the minimum surface
area as calculated above.
Use a concrete pad
where the majority of the solids will settle. Concrete facilitates clean
out. Some producers use concrete pads, others use total concrete, and
some use no concrete. When using total concrete a continuous vertical
concrete curb along each side helps guide the scraper bucket for cleaning
and protects the sides from eroding.
Outlet.
Design the outlet so the top elevation is 6 inches below the berm.
If the outlet plugs, the liquid will still exit at the outlet location.
Either vertical or horizontal 0.5- to 1-inch slots work. Horizontal slots
are somewhat easier to construct and manage. Location is not critical
for the outlet. It can be near an end or in the middle. It should be located,
however, so it does not interfere with cleanout, and it should not be
directly next to the inlet. A concrete end-wall to push against works
well for concrete basins. Tile risers used as outlets need protection
from the cleanout machinery.
General
guideline summary for settling basins
- Basin surface area
should be at least 1/40th of the drainage area. Using 1/201/10th
of the drainage area allows for better settling plus solids storage,
and is ISUs normal recommendation.
- Basins should be
nearly flat. Use no more than 0.5 percent slope.
- Basins should not
be extremely narrow. Wider, shorter designs are advantageous. The minimum
width that should be used is the width of your loader bucket. Using
a 16-foot minimum width often works well.
- Except for very
large lots settling basins should have concrete bottoms to allow easy
solids removal.
- Concrete curbs
along the side(s) of the settling basin make scraping solids easier.
- Slotted outlets
are most common. The outlet should allow dewatering of the collected
solids.
- Outlets should
generally be in the side of the basin rather than on the end. A concrete
wall to push against on the end facilitates solids loading.
- Settling basins
require continuing management and maintenance. They should have solids
removed frequently to function properly.
|